Data Interpretations: Directions for next 4 data interpretations questions: Answer the data interpretations questions on the basis of the table given below:
A factory produces A, B, C, D and E which is made from spare parts manufactured by machines M1, M2, M3, M4, M5 and M6.A week is considered from Monday to Saturday. Each machine works for a certain number of hours on four to five days of the week as shown in the following table.

.
.
.
.
All products do not need spare parts made by all the machines. The production of spare parts of A, B, C, D and E is done by all the machines independently in that order only.
The following table gives the number of hours required by each machine to product a spare part of each product.
.
.
.
.
Note: One unit each of all parts of a specific product after assembling from a set of that product.
1. How many working days in a week are required to manufacture form a set of product B?
a. 2days
b. 3 days
c. 4 days
d. 5 days.
e. 6 days
2. What is the minimum number of working days required to manufacture three sets of product A?
a. 15 days
b. 16 days
c. 17 days
d. 18 days
e. 12 days
3. A set of which product takes the minimum number of working days to manufacture?
a. B
b. C
c. D
d. E
e. None of these
4. On which day of the week are parts of all the products in the process of being manufacture?
a. Thursday
b. Friday
c. Wednesday
d. Saturday
e. Monday.
Related posts:


June 23rd, 2010 at 12:29 pm
1.b
2.e
3.c